Ionic Digital Sells 737 Bitcoin to Pay for Data Centre Buildout

The Celsius-derived miner offloaded a quarter of its treasury at an average of $83,600 a coin, well above Wednesday's market price near $64,000.

Ionic Digital sold about 737 Bitcoin for roughly $61.6 million after the end of September and will spend the proceeds developing its own data centre sites, the miner carved out of Celsius’s bankruptcy disclosed in its latest quarterly report.

The coins went at an average of $83,600 each, net of trading costs, according to the 10-Q filing. The sale cut the company’s holdings by about 25% from its 30 September balance of 2,954 Bitcoin, which was itself up from 2,719 at the end of 2025, leaving roughly 2,217 coins. The filing does not say when the sales took place. Bitcoin traded near $64,000 on Wednesday, about 23% below Ionic’s average disposal price.

Ionic was formed in January 2024 to take over the assets of Celsius Mining under the failed lender’s Chapter 11 plan and began as a pure Bitcoin miner running ASIC fleets at owned and hosted sites. That changed in October 2025, when it signed a lease with a single tenant for its Ward County, Texas, facility, previously called Cedarvale, running through January 2037.

The third quarter shows how far the shift has gone. Revenue rose to about $49.0 million from $37.1 million a year earlier, with digital infrastructure leasing contributing $43.9 million while mining revenue fell to $5.1 million from $37.1 million. The company swung to a net profit of $17.4 million from a $4.5 million loss, a result that included a $73.2 million gain on the fair value of its Bitcoin, partly offset by a $65.9 million loss from remeasuring warrants. For the first nine months of the year it posted a net loss of $30.9 million.

In February the company amended the Ward County lease so the tenant must take another 89 megawatts when available. Control of that capacity had not passed to the tenant by the end of September, so no revenue has been booked on it, and about $19.6 million remains payable on transformer purchases and a substation expansion at the site.

The conversion has cost Ionic mining capacity. The company said it has no room at its owned and leased sites to relocate all the machines it used to run and has decommissioned some of them. It went public through a direct listing on 28 July after raising $400 million in a private placement before $16.7 million of costs, and held about $381.4 million of cash and equivalents at 30 September.

Ionic is one of several listed miners converting Bitcoin into cash for computing projects this month. MARA sold 13,597 Bitcoin for $1.1 billion and said more sales were coming, Core Scientific plans to exit mining by year-end, and Hyperscale Data sold its last coins to fund an AI data centre.