Miners Signed Billion-Dollar AI Contracts. The Building Still Needs Financing

Headline lease values do not pay contractors, and the gap is being filled by credit support, prepayments and equipment-backed loans.

The pitch from bitcoin miners turned AI landlords is straightforward: a signed multi-year lease with a hyperscaler converts a volatile mining business into contracted cash flow. The financing behind those buildings is a separate story, and it is where the risk sits.

TeraWulf offers the clearest example. The company has obtained credit support from Google for approximately $19 billion of Anthropic lease commitments, according to its Nov. 4 announcement. The arrangements back anticipated project financing at its Justified campus in Kentucky, where Fluor is handling engineering and construction across three buildings scheduled to begin entering service in late 2027. The value of that support is not cash. It is a second name on the obligation, which lets a lender underwrite a long construction period with some protection if the tenant does not perform. For the operator, the work of completing buildings and negotiating terms remains.

The arithmetic of a headline lease is worth walking through because it is routinely misread. The Anthropic lease runs 20 years. Dividing $19 billion by 20 produces a simple annual average of about $950 million, before accounting for the actual payment schedule or the phasing of buildings. That figure is not forecast revenue, operating profit or cash available to shareholders in any given year. It is a unit of comparison. An operator cannot hand a contractor a 20-year contract as payment. Borrowing converts expected future receipts into construction funding, and the loan carries interest and covenants. A hypothetical $950 million annual receipt would first have to cover maintenance, staffing, insurance and debt service before it became a return on invested capital.

Other companies with mining roots are solving the same problem differently. IREN has combined a customer prepayment from Microsoft with loans secured against GPUs and contracted payments. The two approaches sit at opposite ends of the timeline: a prepayment is money now against a promise later, while equipment debt is money now against hardware that depreciates faster than the contract runs.

TeraWulf’s Kentucky package was reported in July as potentially combining leveraged loans and high-yield bonds. That reporting described a proposal, not a completed borrowing. The distinction matters because loan announcements frequently confuse a committed facility with a drawn balance, and borrowing may depend on construction milestones and specified uses of proceeds.

Who bears the equipment bill depends on the commercial agreement. A landlord leasing equipped space buys the power and cooling and someone else’s servers; a cloud provider selling compute must acquire GPUs, networking and storage itself. The first model is closer to real estate and the second is closer to a technology business with a shorter asset life.

The disclosures that will settle the question are project-level rather than corporate-level: how much of each facility has been drawn, at what rate, and when the first building is energised. A headline contract value tells a lender little. A drawn balance tells an investor what the company already owes.

The sector’s re-rating rests on the assumption that AI capacity demand persists for the length of these contracts. What the filings show is that the contracts have been signed, the credit support is partial and specific, and the construction financing is still being assembled building by building.